i.
This Monthly
Environmental Monitoring and Audit (EM&A) Report is prepared for Contract
No. SPW 07/2020 ¡§Environmental Team for Construction of Yuen Long Effluent
Polishing Plant Stage 1¡¨. Drainage Services Department (DSD) has appointed
Fugro Technical Services Limited (FTS) to undertake the Environmental Team
services for the project and implement the EM&A works.
ii. This is the 1st Monthly EM&A Report for the Contract
which summaries findings of the EM&A programme during the reporting period
from 8 April 2021 to 30 April 2021. As informed by the Contractor, major
activities in the reporting month were:
¡P
Overhaul
of Detritor;
¡P
Overhaul
of Primary Sedimentation Tank and Final Sedimentation Tank;
¡P
Overhaul
of Sludge Holding Tank and Sludge Digestion Tank;
¡P
Pre-drill
work by 4 drill rig;
¡P
Installation
of instrumentation;
¡P
Site
formation work at IW within piling area;
¡P
Site
formation works at temporary storage area, admin. Building & work shop;
¡P
Erection
of noise barrier;
¡P
Erection
of bird curtain; and
¡P
Trial
pit for zone 1 diversion work & pre-drill work.
Breaches of Action and Limit Levels
iii. No Action and Limit Level exceedance was recorded for air
quality monitoring and construction noise monitoring in the reporting month.
iv. An Action Level exceedance was recorded for water quality in
the reporting month. The exceedance was recorded at M3 on 13 April 2021. It was
found that this exceedance is not project related.
v. No Action / Limit exceedance was recorded for noise levels at
stations (NMS1 and NMS2) in close proximity to the active ardeid night roosts.
vi. Action and Limit levels for the ecological bird monitoring
were not computed due to insufficient data for comparison. Due to the safety
concern encountered during the night-time survey, the monitoring activity was
stopped because of the potential attacks by the village dogs. Night-time survey
activity was suspended to avoid further safety incident. Safety issues shall be
addressed, specifically coordinating with and requesting the dog owners to keep
their dogs within their premises during the duration of the night-time survey.
In connection to this, continued coordination with the dog owners and/or
village representative is currently being undertaken to ensure that the dogs be
kept within their owners¡¦ premises during the monthly ecological survey period;
and/or engage dog owners or local villagers (each from Fung Lok Wai and Nam
Sang Wai) to accompany the team during the monitoring activities.
Complaint Log
vii. No complaints were received in the reporting period.
Notifications of any Summons and
Successful Prosecutions
viii. No notifications of summons and prosecutions were received in
the reporting period.
Reporting Change
ix. There were no reporting changes during the reporting month.
Future Key Issues
x. The main works will be anticipated in the next three months
are as follow:
¡P
Trial
pits excavation;
¡P
Pre-drilling
works;
¡P
Temporary
Sewerage/Sludge diversion -Zone 1 & 2;
¡P
Demolition
of PST no. 7 & 8;
¡P
Piling
works;
¡P
Construction
of Temporary Admin. Building, Workshop, Temporary Storage Facility and MIC
office; and
¡P
Overhaul
works of A-tank, Sludge Holding Tank, FST, PST and Sludge Digestion Tanks.
Contents
3. NOISE
8. ENVIRONMENTAL
COMPLAINT AND NON-COMPLIANCE
9. IMPLEMENTATION
STATUS OF ENVIRONMENTAL MITIGATION MEASURE
Tables
Table 1.1 Contact Information of Key Personnel
Table 1.2
Environmental Licenses, Notification and Permits Summary
Table 2.1
Air Quality Monitoring Equipment
Table 2.2
Air Quality Monitoring Location
Table 2.3 Summary of Air
Quality Monitoring Results
Table 2.4 Comparison of 1-hr TSP
data with EIA predictions
Table 3.1
Construction Noise Monitoring Equipment
Table 3.2
Monitoring Parameters and Frequencies of Noise Monitoring
Table 3.3
Construction Noise Monitoring Location
Table 3.4
Summary of Construction Noise Monitoring Results
Table 3.5
Comparison of Noise monitoring data with EIA predictions
Table 4.1 Water Quality Monitoring and Sampling
Equipment
Table 4.2 Monitoring Parameters and Frequency
Table 4.3
Coordinates of Water Quality Monitoring Locations
Table 4.4
Summary of Water Quality Exceedance
Table 5.1
Noise Monitoring Parameters (For Active Ardeid Night Roost Survey)
Table 5.2
Active Ardeid Night Roost Survey Findings
Table 5.3
Noise Monitoring Results (For Active Ardeid Night Roost Survey)
Table 5.4
Noise Monitoring Parameters
Table 5.5
Abundance of all Avifauna Species
Table 5.6
Abundance of Species of Conservation Importance
Table 5.7
Shannon Diversity Index Value of all Avifauna Species
Table 5.8
Shannon Diversity Index Value of Species with Conservation Importance
Table 5.9
Wetland habitat utilization of all avifauna species
Table 5.10
Wetland habitat utilization of conservation importance
Table 5.11
Wetland habitat utilization of overwintering avifauna species
Table 5.12
Noise Monitoring Results (For Ecological Monitoring of Birds)
Table 7.1 ¡V Waste Generated by the Construction and Disposal Ground
Figures
Figure 1 General Layout of the Proposed Yuen Long Effluent
Polishing Plant
Figure 2 Air Quality Monitoring Locations
Figure 3 Noise Monitoring Locations
Figure 4 Water Quality Monitoring Locations
Figure 5 Ecology Monitoring Locations
Appendices
Appendix A Construction Programme
Appendix B Project Organization Chart
Appendix C Action and Limit Levels
Appendix D Calibration Certificate of Monitoring
Equipment
Appendix E Environmental Monitoring Schedule
Appendix H Event and Action Plan
Appendix J Implementation Status of Environment
Mitigation Measures
Appendix K Weather and Meteorological Conditions
Appendix L Cumulative statistics on Environmental
Complaints, Notifications of Summons and Successful Prosecutions
Appendix
M Summary of Observations and Findings in the
Reporting Month
Appendix
N Outstanding Issues and Deficiencies
Appendix
O Active Night Roost Monitoring Area and Vantage
Points; and Noise Monitoring Stations
Appendix
P Ecological Bird Monitoring Area with Locations
of Point Count Sites and Transect Route
Appendix
Q Notification of Exceedance